600W wind turbine The Tower Foundation , triangle roof installation

 

 
I, Foundation Guide for CXF-600W

 

Before construction the foundation for the CXF-600W system, read these instructions carefully. These instructions are only intend to be guide for concrete foundation on solid soils or suitable roof infrastructure. Please contact your local civil or structure engineer for more information.

 

1. Pole's positioning (built roof)
2. Box of  batteries group
3. Installation of ground wire, foundation cage
4. Pour concrete (40% ~ 50%)
5. Install battery lead hose
6. Pour concrete (100%)
7. Install the battery
8. Assemble the turbine
9. Tower parts assembly (connect turbne, solar panels, and others)
10. Lifting
11. Debugging ( tower, solar panels.)
12. Install the controller
13. Clean up the site
 
 
II, Ground Foundation
 
Lightning angle iron end inserts in the bottom of the Earth, can only achieve conductive effect. Fastening the cage wire terminals of the Foundation. Place ground cage, require vertical laying, foundations should be two or three centimeters below ground level at the top of the cage, parallel to the road, its center point location and road edge distances according to the drawing requirements and consistent (usually set distance of 50~60 cm)
 
1. Grounding electrodes into the underground, insert at the bottom of the well mud 40 ~ 50 cm
 
2. Lead fastening connection terminal and the foundation of cage
 

Add the concrete, using a vibration poker to remove air voids from the pour. It is very important to make sure that the all four rods are hooked under the rebar. Once the concrete is all poured, make sure that the template has no air voids directly underneath. More importantly, make sure the template is leveled off.

Next, clear excess concrete from above template and use a suitable cover to prevent the foundation from rain. Wait until the concrete has set complete before removing the template (It will take at least for one week).  Just remember, a solid with perfect leveled foundation is one of the key factors to achieve the success of installation.

 


Send message to this supplier
Mr. Juan
Tel: 86-755-33872751
Enter between 20 to 3,000 chatacters.
Contact Method
Shenzhen TYPMAR Wind Energy Technology Co.,Ltd
Add: 6FL Yinshan BLDG, beside 107 NR. Fuyong Town, Baoan DIST, Shenzhen, Guangdong, China (Mainland)
Didn't find what you're looking for? Post Buying Lead or contact our customer service specialist for help!